The Transformer header

Project overview

New Energy Centre night smallThe University is investing in infrastructure to ensure resilience and energy security for our world-leading multi-million pound research projects.

The new Transformer will provide an uninterrupted power supply to research experiments and ensure business continuity to the west of campus.

The energy centre will have the capacity to supply power and heat to a number of key University buildings. The new development will lower the cost of heat and electricity for the University.

The architects, Sheffield-based firm HLM, have created a bold design using materials to complement its setting, including Corten on the exterior walls. It received planning permission in May 2018 and construction began in April 2019.


More information

Project details

Project manager: Emel Kus-Senior

Contact: [email] e.kus-senior@sheffield.ac.uk [tel] 0114 222 9003

Architects: HLM Architects

Timescale: September 2018 - April 2020

Latest news

Partial closure of Arts Tower car park from 1 July 2019

We will be working to install pipes under the Arts Tower car park over the summer period. These pipes will form part of a new district heating network for the energy centre (The Transformer).

From 1 July until Wednesday 31 July 2019, all the parking spaces normally only available after 9am will be suspended and some of the category B spaces will be unavailable.

Deliveries from Western Bank will be managed and access routes maintained.

We apologise for any inconvenience caused. For information about alternative car parks, please visit our Parking services pages. 

Gas mains works on Winter Street and Bolsover Street (under the pavement)

Winter Street Fri 26/07/19 -Thu 15/08/19
Bolsover Street Fri 16/08/19 - Thu 12/09/19

Access to the Geography and Arts Tower car parks will be managed during these times. Please expect some disruption to traffic from Winter Street and Bolsover Street on to the site.

Closure of Back Lane - August 2019

Due to the installation of pipes along Back Lane, access to Back Lane will be controlled during August 2019.

As part of works for the Energy Centre, refuse compactors will be moved from the Back Lane behind Firth Court and near the Chemistry Labs to the landing next to Western Bank Library. This is planned for Mid May 2019.

  • Construction activities will start from Monday 8 April 2019. The ground will be prepared for drainage and concrete slab. During weeks 2 and 3, the contractor will carry out drainage works, fill and compact the ground in preparation for the concrete slab.
  • Beginning 18 March 2019: Installation of district heating pipework in the service ducts underground between Geography and Western Bank Library plantrooms. Majority of the works will be undertaken in the underground service ducts and plantrooms. There is expected to be no disruption to users of the Geography building.
  • 18/12/18: We have appointed a main contractor, Vital Energi. They will start on site on 7 January 2019.
  • Planning permission received on 22 May 2018.
  • In early 2018, we demolished the lecture theatre attached to Dainton building.
FAQs
What is the planned duration of the project?

Construction is due to start April 2019 and complete in April 2020.

What work is taking place?

We have demolished a lecture theatre attached to the Dainton Building and will soon begin construction of the New Energy Centre.

How will this affect my journeys around campus?

The New Energy Centre will need to connect with 14 other plant rooms around campus so, as well as the construction of the building, campus will be affected by the digging of trenches to accommodate these connections. When confirmed, we will update the ‘Latest News’ page with a programme of works.

How will I benefit from this project?

All staff and students in the University will benefit from improved business resilience, and a reliable power supply to ensure our research projects are not interrupted.

How will this project affect people who are living and working nearby?

Residents and people working nearby will hear noise from the construction site. Noisy work such as breaking concrete should be completed in July-September 2018. We hope that noise will be minimised during the construction period by many of the units being put together off-site and brought in.

Once the New Energy Centre is up and running, noise should be minimal. The design has focused heavily on attenuation of sound made by fans and the plant equipment.

Why does the University need this supply?

Resilience. A reliable and continuous energy supply is critical to maintaining our research environment.

Will the energy centre contribute to any academic research?

We have agreed that the Department of Chemistry can attach sensors to some of the flues, measuring pollutants.

Will you be landscaping the area with any greenery?

The University’s landscape team is investigating opportunities for adding plants to the area.

Designs

The Transformer

The Transformer

New Energy Centre day

New Energy Centre night

New Energy Centre context

Contact us

Project enquiries: Project Manager Emel Kus-Senior, e.kus-senior@sheffield.ac.uk / 0114 222 9003

General enquiries: The EFM Help Desk will put you in touch with the right person, efmhelpdesk@sheffield.ac.uk / 0114 222 9000